Project Schedule

Construction Timeline
Construction Milestones
Project Start

January 15, 2024

Construction permits approved and site preparation began

Foundation Complete

February 28, 2024

Foundation work completed and passed inspection

Framing Phase

March 15, 2024 - April 5, 2024

Currently in progress - 45% complete

Electrical & Plumbing

April 6, 2024 - April 20, 2024

Scheduled to begin after framing completion

Project Completion

June 30, 2024

Estimated final completion date

Upcoming Tasks
Complete Wall Framing

Due: March 25, 2024

Current
Roof Framing

Due: March 28, 2024

Upcoming
Framing Inspection

Due: April 5, 2024

Upcoming
Begin Electrical Work

Due: April 6, 2024

Upcoming